Loading...

Delays On The US Navy's $161 Billion Virginia-Class Subs Reaches 15 Months

Delays On The US Navy's $161 Billion Virginia-Class Subs Reaches 15 Months - Hallo friend USA IN NEWS, In the article you read this time with the title Delays On The US Navy's $161 Billion Virginia-Class Subs Reaches 15 Months, we have prepared well for this article you read and download the information therein. hopefully fill posts Article HOT, we write this you can understand. Well, happy reading.

Title : Delays On The US Navy's $161 Billion Virginia-Class Subs Reaches 15 Months
link : Delays On The US Navy's $161 Billion Virginia-Class Subs Reaches 15 Months

see also


Delays On The US Navy's $161 Billion Virginia-Class Subs Reaches 15 Months

The USS Texas Virginia-class submarine in the Gulf of Tadjoura. Source: U.S. Navy

Bloomberg: Delays on $161 Billion Virginia-Class Subs Reaches 15 Months

* Average delay of 10.5 months is up from seven-month estimate
* General Dynamics and Huntington Ingalls cite improvements

The Navy’s newest Virginia-class submarines are expected to be 10 to 15 months late as contractors General Dynamics Corp. and Huntington Ingalls Industries Inc. try to recover from assembly faults that have dogged recent boats in the $161 billion program.

The average delay of 10.5 months is an increase from a seven-month average cited in March by the Naval Sea Systems Command for 10 vessels being built under a 2014 contract, according to a comparison of dates in Navy budget documents. The contractors, rival shipbuilders who are producing the submarines together, had sought to shave months off of previous construction periods.

Read more ....

WNU Editor: This is a staggering $161 billion program. These delays must be costing a fortune.


Thus articles Delays On The US Navy's $161 Billion Virginia-Class Subs Reaches 15 Months

that is all articles Delays On The US Navy's $161 Billion Virginia-Class Subs Reaches 15 Months This time, hopefully can provide benefits to all of you. Okay, see you in another article posting.

You now read the article Delays On The US Navy's $161 Billion Virginia-Class Subs Reaches 15 Months with the link address https://usainnew.blogspot.com/2020/02/delays-on-us-navys-161-billion-virginia.html

Subscribe to receive free email updates:

0 Response to "Delays On The US Navy's $161 Billion Virginia-Class Subs Reaches 15 Months"

Post a Comment

Loading...